(Rs. in crores)

Sl.            No. Name of the Projects Estimated cost  Nodal Deptt. Status Remarks
1. Construction of Institute of Human Behaviour & Allied Science (100 Bedded Mental Hospital)          50.00 H&ME DPR sent to DoNER on 27.05.2015  
2. Construction of Multi Level Car Parking at New Secretariat Complex, Aizawl           36.01 UD&PA DPR sent to DoNER on 20.04.2015 Urgent. CS DO was sent to DoNER for early sanction
3. Construction of Housing Complex at Civil Hospital, Lunglei (Total 91 units; Type-1: 18, Type-11: 36, Type-111: 24, Type-IV: 12 and Type-V: 1)          17.31 H&ME DPR and NDC sent to Ministry on 26.09.2013  
4. Construction of Govt. Aizawl College new campus building at Mualpui, Aizawl, Mizoram          12.00 H&TE DPR sent to DoNER on 19.03.2015  
5. Construction of Mizoram State Accounts & Treasury Office          11.01 Finance Clarification to obs from DoNER dated 18.9.2015 sent in the form of revised DPR on 11.12.2015 Urgent. CS DO was sent to DoNER for early sanction
6. Construction of Education Complex at Lunglei (Administrative Building & Teachers Training Complex)          10.40 S.Edu. Clarification to DoNER obs dated 28.8.2015 sent in the form of revised DPR on 21.9.2015 Urgent. CS DO was sent to DoNER for early sanction
7. Construction of 33 KV D/C line tower from 3MW Kau SHP to Thenhlum (17 kms) and Strengthening of 33kV S/s at Thenhlum          10.76  P&E  DPR sent to DoNER on 16.03.2015. Clarification to Ministry's obsv on DPR sent to DoNER on 4.11.2015  
8. Water Supply to Sainik School Chhingchhip            7.87 PHED Clarification to Ministry's obsv on the DPR with estimated cost of Rs.7.75 crore sent to DoNER on 07.04.2016 Urgent. The institute is expected to functional during this financial year
9. Construction of 2×3.15 MVA, 33/11 KV S/s at P&E Complex with associated 33 KV line at Saiha Town            7.66  P&E  DPR sent to DoNER on 17.03.2015. Cost recasted at Rs.8.50 crores.Clarification to observation dated 228.9.2015 sent to Ministry on 4.12.2015  
10. Construction of 2×3.15 MVA, 33/11 KV S/s at P&E Complex with associated 33 KV line in the heart of Lawngtlai Town            6.78 P&E DPR sent to DoNER on 17.03.2015. Cost recasted at Rs.7.10 crores. Clarification to obs dated 6.10.2015 sent on 2.12.2015  
11. Strengthening of Fire & Emergency Services, Mizoram (in Champhai, Lunglei & Kolasib Districts)          10.00 Home
(F&ES)
Revised DPR with clarifications sent to Ministry on 16.01.2015  
12. Construction of Office Building for SP Traffic, Aizawl            5.00 Home
(Police)
DPR and NDC sent to Ministry on 25.10.2013  
13. Infrastructural Requirement of Mizoram Armed Police [Reconstruction of 5 (Five) Border Outposts]            3.30 Home (Police) Revised DPR with clarification to obsv on DPR with estimated cost of Rs.5.25 crore sent to Ministry 06.04.2016.  
14. Improvement of Distribution System within Kolasib District            3.89  P&E  Clarification to Ministry's obsv sent on 04.08.2014. Forwarding letter resubmitted to Ministry on 16.03.2015. DPR recasted at Rs.4.94 crores  
15. Infrastructural Development of Labour, Employment & Industrial Training Department          10.00 L&E Revised DPR sent to Ministry on 19 03.2015. Forwarding letter resubmitted to Ministry on 16.03.2015. Fresh obs on DPR dated 1.1.2016 clarified and sent to Ministry on 29.1.2016  
16. Improvement of Distribution System within Mamit District            4.12 P&E Revised DPR sent to Ministry on 13.06.2014. Three copies of revised DPR (Rs.494.07 lakhs) requested by the Ministry on 08.12.15, and again on 22.02.16  
17. Construction of Aizawl City Bus Terminal -cum-Maxi Cabs Terminal Building at Aizawl South (Melthum)            5.00 Transport DPR and NDC sent to Ministry on 27.01.2014. Clarification to Ministry's observation on DPR sent/submitted to Ministry on 15.2.2016  
18. Construction of Chakhei to Siasi Road            6.46 MADC Certificate of land availability sent to Ministry on 28.08.2014  
19. Construction of Multipurpose Centre at Khatla South            5.97 UD&PA Revised DPR sent Ministry on 26.03.2014. Enquiry on status sent to ministry on 01.04.2015  
20. Construction of Water Reservoirs for Various Fire Stations in Mizoram            3.30 F & ES Obsv on DPR sent to Home for compliance on 24.10.2013. Revised DPR of  Rs.3.855 cr sent to Ministry on 29.10.2015  
21. Construction of Students Hostel at Aizawl in respect of Chakma Autonomous District Council            6.02 CADC New obsv on DPR sent to CADC for clarification on 31.07.2015. Revised DPR sent to Ministry on 4.11.2015  
22. Construction of Estd of TNT Rehab Centre for Persons with Disabilities at Muanna Veng Aizawl, Mizoram                    (Establishment of TNT Mental Hospital at Muanna Veng, Aizawl, Mizoram)            4.94 H&ME Request of Ministry for changing the title of the project complied by the State  
23. Rajiv Gandhi Stadium, Mualpui (C/o Composite Structure of Eastern Gallery)          15.00 PWD DPR and NDC sent to Ministry on 06.03.2013. MoUD obsv on DPR sent to PWD for clarification Clarification Pending from State Govt.
24. Upgradation of Jawaharlal Nehru 100 Bedded Hospital at Serchhip          17.00 H&ME New DPR with revised cost sent to Ministry on 04.06.2015. Fresh obsv on project cost dt.6.1.2016 received from Ministry and forwarded fro H&ME for clarification Clarification Pending from State Govt.
25. Construction of Mini Sports Complex, Sakawrdai *            3.50 S&YS (MSSC) DPR and NDC sent to Ministry on 14.08.2013.  Clarification to obsv sent to ministry on 18.06.2015.  Fresh obsv sent to S&YS for clarification on 28.5.15 Clarification Pending from State Govt.
26. Construction of Mini Sports Complex at Aibawk            4.00 RD Fresh obsv on DPR dt.1.1.2016 sent to RD for clarification Clarification Pending from State Govt.
27. NIT Water Supply Scheme            5.41 PHED DPR sent to DoNER on 20.04.2015. Obsv on DPR sent to PHE for clarification on 14.10.2015 Clarification Pending from State Govt.
  TOTAL        282.71