ONGOING PROJECTS UNDER NLCPR (27.07.2016) | ||||||||||||||
(Rs in lakhs) | ||||||||||||||
Sl. No. | Name of the Project | Nodal/ Implementing Dept | Date of Sanction / Scheduled Completion | Approved cost | Total Fund Released | UC submitted | UC Pending | Last QPR Submitted | Physical Progress in % & Total Expenditure | |||||
Grant | State Share | |||||||||||||
Instalment with date | Amount | Total | Instalment with date | Amount | Total | |||||||||
I. | Education | |||||||||||||
1 | Infrastructure development of 4 Colleges in Mizoram (Saiha, Lunglei, Serchhip & Zirtiri) | H&TE / PWD | 18.09.09 28.2.11 | 546.32 | 1st - 22.09.09 | 196.68 | 393.36 | 21.85 | 43.70 | 393.36 | June ending 2016 | 99.9% | ||
2nd - 27.12.12 | 196.68 | 26.03.13 | 21.85 | 437.17 | ||||||||||
3rd - | ||||||||||||||
2 | Infrastructure Development of Lawngtlai College | H&TE / PWD | 03.05.11 30.04.13 | 136.09 | 1st - 04.05.11 | 48.99 | 85.83 | 11.08.15 | 5.44 | 9.53 | 48.99 | 36.84 | March ending 2016 | 87% |
2nd - 26.02.16 | 36.84 | 01.06.16 | 4.09 | 53.43 | ||||||||||
3rd - | ||||||||||||||
3 | Construction of Multi-Complex Building, Auditorium at Pachhunga University College | PWD | 23.12.10 31.10.12 | 285.26 | 1st - 27.12.10 | 102.69 | 205.38 | 05.07.16 | 11.41 | 22.82 | 205.38 | March ending 2016 | 87% | |
2nd - 25.03.15 | 102.69 | 11.08.15 | 11.41 | 216.79 | ||||||||||
3rd - | ||||||||||||||
4 | Infrastructural Development of Government Champhai College | H&TE / PWD | 17.03.11 31.03.13 | 951.29 | 1st - 21.03.11 | 342.46 | 742.62 | 26.03.12 | 38.05 | 82.51 | 742.62 | Dec ending 2015 | 100% | |
2nd - 06.06.13 | 342.46 | 27.02.16 | 38.05 | 787.08 | ||||||||||
3rd - 17.02.15 | 57.70 | 11.08.15 | 6.41 | |||||||||||
5 | Infrastructure Development of 10 Colleges (T.Romana, Johnson, Aizawl West, J.Thankima, Aizawl North, Hnahthial, J.Buana, Khawzawl, Saitual, Kolasib) | H&TE / PWD | 24.06.11 30.06.13 | 1,367.64 | 1st - 27.06.11 | 482.70 | 1,063.28 | 26.03.12 | 68.92 | 97.31 | 738.22 | 325.06 | Mar ending 2016 | 86% |
2nd - 29.12.14 | 255.52 | 11.08.15 | 28.39 | 826.15 | ||||||||||
3rd - 27.06.16 | 325.06 | |||||||||||||
6 | Construction of Boys & Girls Hostel at Saitual & Thingsulthliah | PWD | 04.07.11 30.06.13 | 189.99 | 1st - 06.07.11 | 67.98 | 169.26 | 21.03.12 | 7.83 | 15.38 | 135.96 | 33.30 | March ending 2016 | 100% |
2nd - 13.12.13 | 67.98 | 11.08.15 | 7.55 | 151.06 | ||||||||||
3rd - 15.12.15 | 33.30 | |||||||||||||
7 | Establishment of Sainik School at Chhingchhip | Home / Pvt Firm | 29.02.12 28.02.15 | 5,064.23 | 1st - 29.02.12 | 1,787.38 | 4,468.42 | 198.59 | 486.54 | 3,574.76 | 893.66 | Dec ending 2014 | 82.00% | |
2nd - 30.08.13 | 1,787.38 | 27.02.16 | 198.59 | 3,410.29 | ||||||||||
3rd - 24.02.15 | 893.66 | 27.02.16 | 89.36 | |||||||||||
8 | Infrastructure Development of Kamalanagar College | CADC | 17.09.12 30.09.14 | 224.00 | 1st - 17.09.12 | 80.64 | 201.60 | 8.96 | 22.40 | 152.18 | 49.42 | Dec. ending 2014 | 74% | |
2nd - 03.02.14 | 71.54 | 7.95 | 152.18 | |||||||||||
3rd - 24.02.15 | 49.42 | 11.08.15 | 5.49 | |||||||||||
9 | Construction of Lai Students Hostel at Aizawl | LADC | 17.10.12 31.10.14 | 596.72 | 1st - 17.10.12 | 214.82 | 429.64 | 23.87 | 47.74 | 429.64 | Dec ending 2015 | 80% | ||
2nd - 24.12.15 | 214.82 | 11.08.15 | 23.87 | 477.38 | ||||||||||
3rd - | ||||||||||||||
10 | Construction of Higher Secondary School Buildings at Kawlkulh and Kawlbem in Mizoram | S.Edu / PWD | 20.12.12 31.12.14 | 195.88 | 1st - 27.12.12 | 70.50 | 141.00 | 11.08.15 | 7.83 | 15.66 | 70.50 | 70.50 | March ending 2016 | 87% |
2nd - 25.02.16 | 70.50 | 01.06.16 | 7.83 | 78.33 | ||||||||||
3rd - | ||||||||||||||
11 | Construction of School building Phase-II within LADC | LADC | 23.09.13 31.08.16 | 1,109.65 | 1st - 26.09.13 | 399.55 | 399.55 | 44.39 | 44.39 | 399.55 | Dec ending 2015 | 100% | ||
2nd - | 443.94 | |||||||||||||
3rd - | ||||||||||||||
12 | Construction of Mara Students Hostel at Aizawl | MADC | 23.09.13 31.08.16 | 538.36 | 1st - 26.09.13 | 197.81 | 391.62 | 11.08.15 | 21.53 | 43.07 | 193.81 | 193.81 | Sept ending 2014 | 40% |
2nd - 11.03.16 | 193.81 | 05.07.16 | 21.54 | 108.00 | ||||||||||
3rd - | ||||||||||||||
13 | Construction of Hostels for Students of Higher Secondary Schools | S.Edu. | 29.12.14 30.06.15 | 520.48 | 1st - 29.12.14 | 187.37 | 187.37 | 01.06.16 | 41.64 | 41.64 | 187.37 | |||
2nd - | ||||||||||||||
3rd - | ||||||||||||||
Total | 11,725.91 | 8,878.93 | 972.69 | 7,084.97 | 1,789.96 | |||||||||
II. | Health | |||||||||||||
14 | Construction of Medical Staff quarters for CHC at Saitual & Thingsulthliah (6 nos. of Type-II, 2 nos of Type-IV each) | HS / PWD | 03.05.11 31.03.12 | 132.21 | 1st - 04.05.11 | 46.62 | 46.62 | 28.03.14 | 5.81 | 5.81 | 46.62 | Dec ending 2015 | 87% | |
2nd - | 51.84 | |||||||||||||
3rd - | ||||||||||||||
15 | Construction of 100 Bedded Hospital, Saiha | HME / PWD | 23.09.13 31.08.16 | 1,592.52 | 1st - 26.09.13 | 573.31 | 573.31 | 63.70 | 63.70 | 573.31 | March ending 2016 | 38% | ||
2nd - | 443.04 | |||||||||||||
3rd - | ||||||||||||||
16 | Construction of 50 Bedded Hospital at Lawngtlai | HME / PWD | 29.12.14 31.12.16 | 1,191.51 | 1st - 30.12.14 | 429.94 | 429.94 | 05.07.16 | 47.66 | 47.66 | 428.94 | |||
2nd - | ||||||||||||||
3rd - | ||||||||||||||
Total | 2,916.24 | 1,049.87 | 117.17 | 46.62 | 1,002.25 | |||||||||
III. | Miscellaneous | |||||||||||||
17 | Upgradation of Lawngtlai Town | LADC | 03.05.11 30.4.14 | 1,181.74 | 1st - 04.05.11 | 417.09 | 1,042.71 | 46.34 | 115.85 | 834.18 | 208.53 | March ending 2016 | 96.08% | |
2nd - 20.11.12 | 417.09 | 46.34 | 1,135.39 | |||||||||||
3rd - 17.02.15 | 208.53 | 27.02.16 | 23.17 | |||||||||||
18 | Upgradation of Lengpui Airport in Mizoram | Civil Aviation / PWD | 21.02.11 & 15.03.11 | 2,481.62 | 1st - 17.03.11 & 21.02.11 |
875.47 | 1,296.37 | 07.08.12 & 11.03.14 | 97.28 | 144.05 | 1,296.37 | March ending 2016 | 95% | |
28.02.13 | 2nd - 18.12.15 | 420.90 | 11.08.05 | 46.77 | 1403.58 | |||||||||
3rd - | ||||||||||||||
19 | Strengthening of Govt. Press | P&S | 15.03.11 31.03.12 | 842.47 | 1st - 17.03.11 | 297.34 | 730.33 | 33.04 | 81.15 | 594.68 | 135.65 | Dec ending 2014 | 80% | |
2nd - 06.09.12 | 297.34 | 33.04 | 660.77 | |||||||||||
3rd - 11.12.14 | 135.65 | 15.07 | ||||||||||||
20 | Construction of Multi-level Parking, Community Centre & Office at Aizawl 'N' | S&YS / PWD | 16.12.11 31.10.13 | 1,298.26 | 1st - 16.12.11 | 458.21 | 458.21 | 50.91 | 50.91 | 458.21 | June ending 2014 | nil | ||
2nd - | nil | |||||||||||||
3rd - | ||||||||||||||
21 | Construction of 10 Helipads in Mizoram | Civil Aviation / PWD | 12.9.2012 30.9.13 | 258.20 | 1st - 12.09.12 | 92.95 | 92.95 | 11.08.15 | 10.32 | 10.32 | 92.95 | March ending 2016 | 80% | |
2nd - | 103.27 | |||||||||||||
3rd - | ||||||||||||||
22 | Modernization of Kamalanagar Town | CADC | 23.10.12 31.10.14 | 1,988.82 | 1st - 25.10.12 | 715.98 | 1,431.96 | 79.55 | 159.20 | 1,431.96 | June ending 2014 | 50% | ||
2nd - 03.02.14 | 715.98 | 79.65 | 997.43 | |||||||||||
23 | Construction of Market Building Vairengte | RD / PWD | 01.07.13 30.06.15 | 387.65 | 1st - 02.07.13 | 139.55 | 139.55 | 01.06.16 | 15.51 | 15.51 | 139.55 | |||
2nd - | ||||||||||||||
3rd - | ||||||||||||||
24 | Construction of Multipurpose Centre at Ramthar N, Aizawl | UD&PA | 18.02.14 31.08.16 |
462.37 | 1st - 20.02.14 | 166.45 | 166.45 | - | 166.45 | |||||
2nd - | ||||||||||||||
3rd - | ||||||||||||||
25 | Infrastructure Requirement of Police (Estd of 3rd IR Bn. Hq. at Thingkah, Lawngtlai) | Home | 03.03.14 31.08.16 | 2,842.28 | 1st - 04.03.14 | 1,023.22 | 2,046.44 | 11.08.15 | 113.69 | 113.69 | 1,023.22 | 1,023.22 | Dec ending 2015 | 40.00% |
2nd - 16.03.16 | 1,023.22 | 1023.22 | ||||||||||||
26 | Upgradation of Central Jail, Aizawl - For Construction of Separate Women's Jail | Home | 29.12.14 31.12.17 |
1,306.95 | 1st - 30.12.14 | 470.50 | 470.50 | 27.02.16 | 43.56 | 43.56 | 470.50 | |||
2nd - | ||||||||||||||
3rd - | ||||||||||||||
27 | Construction of Police Headquarters Building at Khatla | Home | 30.12.14 31.12.17 |
1,555.79 | 1st - 30.12.14 | 560.08 | 560.08 | 01.06.16 | 43.56 | 43.56 | 560.08 | March ending 2016 | 45% | |
2nd - | 625.00 | |||||||||||||
3rd - | ||||||||||||||
28 | Construction of Multi-shopping Complex at Saitual | RD | 16.11.15 31.12.17 |
310.33 | 1st - 17.11.15 | 111.72 | 111.72 | 05.07.16 | 12.41 | 12.41 | 111.72 | |||
2nd - | ||||||||||||||
3rd - | ||||||||||||||
29 | Construction of High Court Building at New Secretariat Complex, Aizawl | L&J | 18.03.16 28.02.19 |
4,624.12 | 1st - 15.03.16 | 1,471.90 | 1,471.90 | 05.07.16 | 163.54 | 163.54 | 1,471.90 | |||
2nd - | ||||||||||||||
3rd - | ||||||||||||||
Total | 19,540.60 | 10,019.17 | 953.75 | 5,833.44 | 4,185.73 | |||||||||
IV. | Power | |||||||||||||
30 | Construction of 132 kV S/C line on D/C towers from Kolasib to Aizawl (Melriat) with LILO of one circuit at Aizawl (Zuangtui) 132 kV Sub Station | P&E | 22.12.05 31.12.08 | 2,151.10 | 1st - 22.12.05 | 677.60 | 1,703.67 | 75.29 | 189.30 | 1,703.67 | March ending 2016 | 96.18% | ||
2nd - 26.09.07 | 677.60 | 75.29 | 1,703.67 | |||||||||||
3rd - 21.03.11 | 348.47 | 38.72 | ||||||||||||
31 | Construction of 110 Kms 132kV S/C Aizawl (Melriat S/S)-Lunglei Line including one outgoing Bay at Melriat and one incoming Bay at Lunglei | P&E | 12.09.12 30.9.15 | 4,176.07 | 1st - 12.09.12 | 1,503.38 | 3,006.46 | 11.08.15 | 167.04 | 334.08 | 1,503.38 | 1,503.08 | March ending 2016 | 58% |
2nd - 23.09.15 | 1,503.08 | 01.06.16 | 167.04 | 2,459.32 | ||||||||||
3rd - | ||||||||||||||
Total | 6,327.17 | 4,710.13 | 523.38 | 3,207.05 | 1,503.08 | |||||||||
V. | Road & Bridges | |||||||||||||
32 | Construction of 3 Bailey Bridges in Mizoram | |||||||||||||
1) Bailey Bridge over R.Tuikum on Chhingchhip-Hmuntha Road (span 50m) | PWD | 26.09.06 31.12.08 | 211.24 | 1st - 21.04.11 | 74.98 | 74.98 | 8.33 | 8.33 | 74.98 | nil | March ending 2016 | 100% | ||
2nd - | 83.31 | |||||||||||||
3rd - | ||||||||||||||
2) Bailey Bridge over R.Lunghmultui on Lengpui-W.Serzawl Road (span 40 m) | 190.50 | 1st - | 58.20 | 161.75 | 6.47 | 17.97 | 161.75 | nil | March ending 2016 | 100% | ||||
2nd - 21.04.11 | 103.55 | 11.50 | 173.25 | |||||||||||
3rd - | ||||||||||||||
3) Bailey Bridge over R.Tuisa on Kawlbem-Vaikhawtlang Road (span 50 m) | 247.68 | 1st - | 71.39 | 142.78 | 7.92 | 15.85 | 142.78 | nil | March ending 2016 | 100% | ||||
2nd - 29.12.11 | 71.39 | 7.93 | 158.62 | |||||||||||
3rd - | ||||||||||||||
33 | Construction of Bamboo Plantation Link Road from Saiphal to Hortoki (0-27.5 km) | PWD | 12.01.06 31.12.08 | 1,300.00 | 1st - 14.12.06 | 409.40 | 818.80 | 45.49 | 818.80 | Sept ending 2015 | 74% | |||
2nd - 03.06.11 | 409.40 | 45.49 | 864.29 | |||||||||||
3rd - | ||||||||||||||
34 | Construction of Bamboo Plantation Link Road to proposed Bamboo Plantation Areas from Tuirial Airfield to Bukpui Phase I (0-40) | PWD | 12.12.06 31.12.08 | 2,239.02 | 1st - 15.12.06 | 705.29 | 705.29 | 4.05 | 4.05 | 705.29 | nil | Sept ending 2015 | 37.75% | |
2nd - | 705.29 | |||||||||||||
3rd - | ||||||||||||||
35 | Construction of Bamboo Plantation Link road from Tuirial airfield to Bukpui Phase-II (40-84) | PWD | 12.12.06 31.12.08 | 2,512.50 | 1st - 21.12.06 | 791.44 | 791.44 | 87.94 | 87.94 | 791.44 | nil | Sept ending 2015 | 43% | |
2nd - | 879.37 | |||||||||||||
3rd - | ||||||||||||||
36 | Construction of Longpuighat – Kukurduleya Road | CADC | 03.02.09 28.2.11 | 1,152.45 | 1st - 04.02.09 | 344.69 | 1,016.87 | 38.29 | 112.98 | 689.38 | 327.49 | June ending 2014 | 80% | |
2nd - 17.03.11 | 344.69 | 38.30 | 902.37 | |||||||||||
3rd - 12.12.12 | 327.49 | 36.39 | ||||||||||||
37 | Constn of approach road to: (a) Tuivai from Mimbung (Rs.319.54 lakhs) (b) Godown at Kawlkulh (Rs.40.35 lakhs) (c) 2% Contingency (Rs.7.2 lakhs) |
PWD | 24.06.11 31.12.12 | 367.09 | 1st - 27.06.11 | 129.56 | 204.60 | 14.40 | 22.74 | 129.56 | 75.04 | March ending 2016 | 63.58% | |
2nd - 04.03.16 | 75.04 | 01.06.16 | 8.34 | 219.00 | ||||||||||
3rd - | ||||||||||||||
38 | Construction of Sihpui to Thuampui Road | PWD | 13.12.10 31.12.12 | 248.23 | 1st - 13.12.10 | 87.61 | 219.03 | 9.73 | 24.33 | 219.03 | Dec ending 2015 | 99% | ||
2nd - 19.12.12 | 87.61 | 9.73 | 238.49 | |||||||||||
3rd - 13.12.13 | 43.81 | 05.07.16 | 4.87 | |||||||||||
39 | Construction of Khanpui to Tualbung Road Phase I | PWD | 04.07.11 30.06.12 | 197.21 | 06.07.11 | 69.60 | 124.31 | 7.73 | 13.81 | 99.44 | 24.87 | March ending 2016 | 82.00% | |
2nd - 24.03.15 | 29.84 | 11.08.15 | 3.32 | 135.36 | ||||||||||
3rd - 17.11.15 | 24.87 | 01.06.16 | 2.76 | |||||||||||
40 | Construction of Jeepable Suspension Bridge over R.Chhimtuipui at Darzokai on Hnahthial-Sangau Road | PWD | 02.03.12 28.02.13 | 216.21 | 1st - 06.03.12 | 76.31 | 190.78 | 8.47 | 21.19 | 152.62 | 39.16 | March ending 2016 | 99% | |
2nd - 05.12.14 | 76.31 | 11.08.15 | 8.48 | 207.73 | ||||||||||
3rd - 15.12.15 | 38.16 | 01.06.16 | 4.24 | |||||||||||
41 | Construction of Lawngtlai Bypass Road Phase I (13 Kms) Upto WBM & Bituminous Works) | LADC | 26.11.12 30.11.14 | 1,029.47 | 1st - 27.11.12 | 411.79 | 411.79 | 45.75 | 45.75 | 411.79 | Dec ending 2015 | 40% | ||
2nd - | 457.54 | |||||||||||||
3rd - | ||||||||||||||
42 | Construction of Hnahthial Haulawng via Zotui Road (15Kms) (Upto WBM & Bituminous Works) | PWD | 29.12.14 31.12.17 |
1,515.78 | 1st - 30.12.14 | 545.68 | 545.68 | 11.08.15 | 60.63 | 60.63 | - | 545.68 | ||
2nd - | ||||||||||||||
3rd - | ||||||||||||||
Total | 11,427.38 | 5,408.10 | 481.06 | 4,396.86 | 1,012.24 | |||||||||
VI. | Sports | |||||||||||||
43 | State Sports Academy, Zobawk | S&YS / PWD | 02.08.10 31.07.12 | 1,751.24 | 1st - 02.08.10 | 630.45 | 1,184.72 | 19.03.13 | 70.05 | 70.05 | 547.15 | 637.57 | Dec ending 2015 | 63% |
2nd - 26.08.15 | 554.27 | 596.16 | ||||||||||||
3rd - | ||||||||||||||
44 | Construction of Indoor Stadium at Keitum | S&YS / PWD | 23.12.10 31.12.12 | 173.75 | 1st - 27.12.10 | 62.55 | 120.43 | 05.03.12 | 6.95 | 13.38 | 116.58 | Dec ending 2015 | 100% | |
2nd - 26.11.12 | 40.00 | 01.10.13 | 4.44 | 131.82 | ||||||||||
3rd - 29.09.14 | 17.88 | 27.02.16 | 1.99 | |||||||||||
45 | Construction of Indoor Stadium at Bungtlang | S&YS / PWD | 23.12.10 31.12.12 | 173.75 | 1st - 27.12.10 | 62.55 | 120.43 | 27.02.12 | 6.95 | 14.94 | 124.28 | Dec ending 2015 | 100% | |
2nd - 10.12.13 | 43.85 | 27.02.16 | 6.43 | 113.35 | ||||||||||
3rd - 29.09.14 | 14.03 | 1.56 | ||||||||||||
46 | Additional Works for Construction of Indoor Stadium at Aizawl | S&YS / PWD | 21.02.13 31.08.14 | 245.11 | 1st - 25.02.13 | 88.24 | 174.99 | 11.08.15 | 9.80 | 19.44 | 88.24 | 86.75 | Dec ending 2015 | 80% |
2nd - 25.02.16 | 86.75 | 01.06.16 | 9.64 | 88.24 | ||||||||||
3rd - | ||||||||||||||
47 | Construction of Indoor Stadium at Chanmari, Lunglei | S&YS / PWD | 18.02.14 | 496.19 | 1st - 20.02.14 | 178.63 | 331.26 | 11.08.15 | 19.85 | 39.81 | 178.63 | 152.63 | Dec ending 2015 | 50% |
2nd - 25.02.16 | 152.63 | 01.06.16 | 19.96 | 198.30 | ||||||||||
3rd - | ||||||||||||||
48 | Construction of Zaua Sailo Memorial Tennis Centre, Lunglei | S&YS / PWD | 11.09.15 31.12.17 |
426.00 | 1st - 14.09.15 | 153.43 | 153.43 | 05.07.16 | 17.05 | 17.05 | 153.43 | |||
2nd - | ||||||||||||||
3rd - | ||||||||||||||
49 | Construction of Mini Sports Complex at E.Lungdar | RD | 17.08.15 31.12.17 |
434.96 | 1st - 17.09.15 | 156.58 | 156.58 | 05.07.16 | 17.40 | 17.40 | 156.58 | |||
2nd - | ||||||||||||||
3rd - | ||||||||||||||
50 | Construction of Mini Sports Complex at Khawbung | RD | 07.03.16 30.03.18 |
369.89 | 1st - 07.03.16 | 133.16 | 133.16 | 05.07.16 | 14.80 | 14.80 | 133.16 | |||
2nd - | ||||||||||||||
3rd - | ||||||||||||||
51 | Construction of Table Tennis Training Centre at Mission Vengthlang in Aizawl | UD&PA | 13.10.15 31.12.17 |
369.87 | 1st - 30.10.15 | 133.15 | 133.15 | 01.06.16 | 14.79 | 14.79 | 133.15 | |||
2nd - | ||||||||||||||
3rd - | ||||||||||||||
Total | 4,440.76 | 2,508.15 | 221.66 | 1,054.88 | 1,453.27 | |||||||||
VII. | Water Supply | |||||||||||||
52 | Bilkhawthlir Water Supply Scheme | PHED | 03.05.11 30.04.13 | 780.47 | 1st - 04.05.11 | 275.49 | 550.98 | 30.61 | 61.22 | 550.98 | nil | March ending 2016 | 100.00% | |
2nd - 05.09.12 | 275.49 | 30.61 | 612.20 | |||||||||||
3rd - | ||||||||||||||
53 | Greater Saitual Water Supply Scheme | PHED | 10.12.10 31.03.13 | 2,153.20 | 1st - 12.10.10 | 759.90 | 1,732.52 | 84.43 | 192.50 | 1,732.52 | June ending 2016 | 93.53% | ||
2nd - 19.11.12 | 759.90 | 84.43 | 1,925.02 | |||||||||||
3rd - 13.03.14 | 212.72 | 27.02.16 | 23.64 | |||||||||||
54 | West Phaileng Water Supply Scheme | PHED | 24.06.11 30.06.13 | 995.19 | 1st - 27.06.11 | 358.27 | 716.54 | 39.81 | 79.12 | 716.54 | nil | March ending 2016 | 97.00% | |
2nd - 05.09.12 | 358.27 | 39.31 | 795.66 | |||||||||||
3rd - | ||||||||||||||
55 | South Khawbung Water Supply Scheme | PHED | 16.12.11 31.12.13 | 827.38 | 1st - 16.12.11 | 297.86 | 595.72 | 33.10 | 66.20 | 595.72 | nil | June ending 2016 | 81% | |
2nd - 06.11.12 | 297.86 | 33.10 | 661.92 | |||||||||||
3rd - | ||||||||||||||
56 | Sairang Water Supply Scheme | PHED | 20.3.12 31.3.14 | 221.14 | 1st - 29.06.12 | 78.05 | 156.10 | 8.67 | 8.67 | 78.05 | 78.05 | March ending 2016 | 66.7% | |
2nd - 27.06.16 | 78.05 | 86.72 | ||||||||||||
3rd - | ||||||||||||||
57 | Aibawk Water Supply Scheme | PHED | 23.09.13 31.08.16 | 979.42 | 1st - 26.09.13 | 352.59 | 705.18 | 11.08.15 | 39.18 | 78.36 | 705.18 | 352.59 | March ending 2016 | 80.52% |
2nd - 26.08.15 | 352.59 | 01.06.16 | 39.18 | 744.36 | ||||||||||
3rd - | ||||||||||||||
Total | 5,956.80 | 4,457.04 | 486.07 | 4,378.99 | 430.64 | |||||||||
Grand Total | 62,334.86 | 37,031.39 | 3,755.78 | 26,002.81 | 11,377.17 |